Measure once and plan gates and corners. Then work through posts, infill, concrete and hardware, keeping required quantities separate from what you buy.

Use this guide to: Turn a measured layout into a shopping list, separating required from buy quantities.

Build your materials list →

Worked example: 100 ft cedar with one gate

The layout is 100 ft straight, 6 ft tall, stick-built cedar, 8 ft maximum spacing, one 4 ft walk gate assumed mid-run and 10% waste. These are the calculator's results:

Required = design quantity · Buy = after waste and stock rounding
ItemRequiredBuyWhy they differ
4×4 posts1414No waste added. Add spares yourself.
2×4 rails364012 bays × 3 rails, +10%
Pickets20122296 ft net infill, +10%
Fasteners13501485+10%
Concrete12.89 cu ft22 × 80 lbRounded up to whole bags
Gravel3.82 cu ft8 bags0.5 cu ft bags assumed
Gate + hardware kit1 + 11 + 1Counted per gate

Step by step

  1. Measure and sketch. Walk the line with a long tape or measuring wheel. Mark corners, gates and slopes, and confirm property lines and HOA rules.
  2. Place gates. Use the clear opening the gate hardware needs. The gate's width is removed from fence infill.
  3. Count posts with the post method. Here: 4 terminal + 10 line = 14.
  4. Count infill. Use pickets and rails for stick-built wood, or one panel per bay for prebuilt systems. Never both.
  5. Concrete and gravel per post, rounded to whole bags.
  6. Hardware: exterior-rated fasteners, post caps, hinges and latch.

Matching required quantities to stock sizes

  • The calculator counts rails per bay. With bays of 8 ft or less, 8 ft rails cover one bay each. Some builders use 16 ft rails across two bays to stagger the joints. That halves the rail count but means handling longer boards.
  • Pickets are counted at their actual width (5.5 in for a nominal 1×6). Measure the boards in the store.
  • Fasteners are sold by box or weight. Divide the buy count by the box count and round up.

Leave these off the materials list

Permits, surveys, delivery, tool rental, stain and old-fence removal belong in your budget or quote comparison, not the shopping list. Price them with the cost calculator or ask installers.

Call 811 before digging

811 is the free U.S. call-before-you-dig number. It arranges marking of buried utility lines before you set posts.

Checklist

  • Write down the measured length of every run, and every gate's clear opening.
  • Choose one system: stick-built (rails + pickets) or prebuilt panels.
  • Use Required for planning and Buy for the cart. Add spare posts separately.
  • Convert rails, fasteners and gravel to the stock lengths and package sizes you'll actually buy.
  • List gate hinges, latch, drop rod (for double gates) and post caps.
  • Call 811 before digging.

References and data status

Worked numbers on this page come from this site's calculator engine and its internally authored national U.S. baseline (us-baseline-1.0.0). That baseline is not live, not ZIP-localized and not externally reviewed. This guide relies only on the calculator's own formulas. See the methodology.

    All figures are estimates based on baseline U.S. assumptions, not contractor quotes.

    Frequently asked questions

    How much waste should I plan for?

    The calculator adds a waste allowance (10% by default, adjustable) only to cuttable or breakable items: pickets, rails and fasteners. Posts, concrete and hardware are bought at the required quantity. Add spares yourself if you want them.